ITEM:

Approval of the following evaluation committee for RFP CIP 26-553 Democrat Road Reconstruction.

  • a. Prarthana Banerji, County Engineer - Road and Bridge
  • b. Shawn Eldridge, Assistant General Superintendent - Road and Bridge
  • c. John Talley, Area Supervisor - Road and Bridge
  • d. Legal (non-voting)
  • e. Purchasing (non-voting)

TO:Commissioners Court
FROM:Celina Nava
DATE:04/10/2026
FISCAL IMPACT:False
BUDGETED:False
DOLLAR AMOUNT:$0.00
NOTES/EXCEPTIONS:This committee will evaluate the proposals for the Democrat Road Reconstruction. Democrat Road begins at the end of the Democrat Road Railcar Replacement project and extends approximately 4,300 LF until it intersects Oak Lake Road.